Question: This new exercise physical therapy facility involves very complex mechanical, electrical, and plumbing ( MEP ) systems, totaling over 4 5 % of the entire
This new exercise physical therapy facility involves very complex mechanical, electrical, and
plumbing MEP systems, totaling over of the entire construction budget. The owner had a
bad prior experience with a fully designedbidbuilt mechanical project. Under the
recommendation of the architect and estimating consultant, they decide to employ designbuild
DB mechanical and electrical subcontractors directly.
Legally based on this case do you agree utilization of DB MEP subcontractors helps
control costs?
What role could a thirdparty MEP designer play with respect to criteria
documents How much are design fees for MEP subcontractors?
Who should carry these design contracts, the owner, the architect, or the general
contractor?
Who carries the insurance for this work?
Who is named as additional insured?
What risks do all of the parties assume?
Assume in the above case the client carries the design portion of the MEP contracts and a
negotiated general contractor will ultimately carry the construction portion of the contracts
when a guaranteed maximum price GMP contract is developed. The design agreements are
very loose and the subcontractors deliverables and detailed schedules of values SOVs are not
defined. The subcontractordesign team reports that the documents are complete, and the
general contractor submits their GMP to the owner. It is significantly over their earlier budget,
especially in the areas of mechanical and electrical. The subcontractors refuse to negotiate their
construction estimate and the owner announces they will bid this portion of the work out.
Is this ethical?
Is the owner guaranteed a lower construction price if this portion of the work is put
on the street for open bidding?
Will the original designbuild subcontractors submit competitive lump sum bids on
their own drawings?
If so will they be successful submitting change orders for discrepant documentation?
What are the risks for all parties?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock