Question: This problem is to be worked out manually i . e . with a calculator KraftyCity is a large retailer that sells power tools and

This problem is to be worked out manually i.e. with a calculator
KraftyCity is a large retailer that sells power tools and other hardware supplies. One of its
products is the Krafty-Man workbench. Information on the workbench is as follows:
Annual Demand =1200
Holding cost = $15 per unit per year.
Ordering cost = $200 per order.
a) What is the economic order quantity (EOQ) for the workbench? Show your calculation
clearly.
b) Suppose that KraftyCity has to pay $50 per workbench for order under 200, but only $42
per workbench for orders 201 or more. What order quantity should KraftyCity use?
Compute the total cost as =[ Holding cost + Ordering Cost + Material cost ] for the year
to arrive at your answer. Show your calculation clearly.
c) The lead time for KraftyCity workbench is 3 weeks, with a standard deviation of 1.2
weeks; and the average weekly demand is 24 with a standard deviation of 8
workbenches. What is the safety stock and reorder point, if KraftyCity wants to provide
a 95% customer service level? Show your calculation clearly.
d) Now suppose that the supplier of workbenches guarantees that the lead time will be a
constant 3 weeks (i.e. standard deviation of lead time is now zero). Recalculate the
safety stock and reorder point using the same service level of 95%. Has the safety stock
level increased or decreased? Show your calculation clearly.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!