Question: This process is where start and finish dates for your project activities are determined and activity sequences and durations are finalized. Some of the inputs
This process is where start and finish dates for your project activities are determined and activity sequences and durations are finalized. Some of the inputs to this process include calendars, lead and lags, and activity attributes. Which process is this question describing?
Question Select one:
a
Develop Schedule
b
Sequence Activities
c
Estimate Activity Duration
d
Estimate Activity Resources