Question: This question has all the information needed. The critical path method chart in the left needs filled out and then the two tables on the
This question has all the information needed. The critical path method chart in the left needs filled out and then the two tables on the right need completed. Please look at the picture included
G
B D
E
F
G
H
I
J
Activities:
w
x
r
z
tableActivities:Time Estimates DaysOptimisticMrost,Pessimistic,Expected Duration,Variance,ABCDEFGH
Path:
tablePathtablePath MeanDaystablePathVariancetableResultingscoreArea From zTable,tableProbabilityAssociated with path
The probability that the project can be completed in days or less is:
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
