Question: This question has more than one correct answer and all must be selected Select all the statements that are not true. The assignment method provides

This question has more than one correct answer and all must be selected
Select all the statements that are not true.
The assignment method provides an optimum, one-to-one assignment of resources to staff.
Earliest due date is a shop floor dispatching (sequencing) rule that relates the time available to complete a job to the amount of work left to be completed
The critical ratio sequencing rule prioritizes the jobs based on the importance or value of the customers who have placed the orders.
Dispatching rules are typically judged by four effectiveness criteria: average completion time, utilization, average number of jobs in the system, and average job lateness.
The constat work-in-process (ConWIP) card aids input-output control by limiting the amount of work inaworkcentre.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!