Question: This question is asking to find MRP (Materials Requirements Planning). This is an Operations Management question Materials Planning Requirements (MRP) Practice Problem Bill of Materials:

This question is asking to find MRP (Materials Requirements Planning). This is an Operations Management question
Materials Planning Requirements (MRP) Practice Problem Bill of Materials: Toy Car (1) LT=2 Level 1 Body Assy (0) LT-5 Wheels (4) LT=3 Level 2 Hood (1) LT-3 Top (1) LT=2 Base (1) LT=4 Sides (2) LT-3 Trunk (1) LT-2 Level 3 Week 5 1 2 3 4 6 7 8 9 10 11 12 500 100 Toy Car (LT2) Gross Requirements On-Hand Inventory Net Requirements Planned Order Rec Planned Order Rel 1 2 3 4 5 6 7 8 9 10 11 12 800 Wheels (LT-3) Gross Requirements On-Hand Inventory Net Requirements Planned Order Rec Planned Order Rel 1 2 3 4 5 6 7 8 9 10 11 12 125 Body Assy LT-5) Gross Requirements On-Hand Inventory Net Requirements Planned Order Rec Planned Order Rel 2 3 4 5 1 6 7 8 9 10 11 12 0 Hood (LT-3) Gross Requirements On-Hand Inventory Net Requirements Planned Order Rec Planned Order Rel 1 2 3 4 5 6 8 9 10 11 12 Top (LT=2) Gross Requirements On-Hand Inventory Net Requirements Planned Order Rec Planned Order Rel 100 1 IN 3 4 LO 6 7 8 9 10 11 12 Base (LT-4) Gross Requirements On-Hand Inventory Net Requirements Planned Order Rec Planned Order Rel 175 1 2 4 5 6 7 8 9 10 11 12 Side (LT=3) Gross Requirements On-Hand Inventory Net Requirements Planned Order Rec Planned Order Rel 200 2 3 4 5 6 8 9 10 11 12 Trunk (LT2) Gross Requirements On-Hand Inventory Net Requirements Planned Order Rec Planned Order Rel 300
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock