Question: This question is based on the AoN network diagram below. What is the earliest that Activity D can begin if Activity A takes 3 days,

This question is based on the AoN network diagram below. What is the earliest that
Activity D can begin if Activity A takes 3 days, Activity B takes 5 days, and Activity C
takes 7 days?
A) Day 15
B) Day 7
C) Day 5
D) Day 3
 This question is based on the AoN network diagram below. What