Question: This question is based on the AoN network diagram below. What is the earliest that Activity D can begin if Activity A takes 3 days,
This question is based on the AoN network diagram below. What is the earliest that
Activity can begin if Activity A takes days, Activity B takes days, and Activity C
takes days?
A Day
B Day
C Day
D Day