Q6. Following were the cost estimates developed by a project manager and actual cost incurred for a project running over 8 periods. Calculate Tracking Signal. Were the errors random? (7 marks) 1 4 5 6 7 Period 2. 3 8 Estimate(Rs.) 200,000 250,000 700,000 750.000 800,000 600,000 250,000 50,000 Actual (Rs.) 180,000 220,000 750,000 755,000 860,000 650,000 220,000 60,000Step by Step Solution