Question: This question is regarding network in Operation Management Construct a network diagram for the activities given in figure For each activity. define (a) Earliest start

This question is regarding network in Operation Management
Construct a network diagram for the activities given in figure
For each activity. define
(a) Earliest start time.
(b) Earliest finish time.
(c) Latest start time.
Construct a network diagram for the activities given in Figure FIGURE 10.32 11 ACTIVITY IMMEDIATE PREDECESSORS 1 2 3 5 6 7 8 9 10 11 12 2 1.3 2 1.3.5 1.3.5 2 4.6 4.6 - 7.8.9 10.11 Build-Rite has estimated the times given in Figure 10.33 as ne each of the tasks involved in building a house. For each activity, define (a) Earliest start time. (b) Earliest finish timc. (c) Latest start timeStep by Step Solution