Question: THIS QUESTION PROJECT MANAGEMENT QUESTION The normal cost for the tools of an R&D project is 75 TL. project supervisor demonstrated with the most appropriate
THIS QUESTION PROJECT MANAGEMENT QUESTION
The normal cost for the tools of an R&D project is 75 TL. project supervisor demonstrated with the most appropriate security that can be exploited by the project. given below what is the minimum cost to be planned to build the table, calculate
| Activity | Normal Time | Minimum Time | Shortening cost (TL/day) | priority activity |
| A | 10 | 6 | $200 | _ |
| B | 6 | 3 | $90 | _ |
| C | 2 | 2 | _ | B |
| D | 4 | 2 | $80 | C |
| E | 6 | 4 | $160 | A |
| F | 8 | 5 | $300 | D,E |