Question: This section of the assignment covers project management with a focus on network development and crashing. The project parameters are: Project Parameters Task Length (weeks)

This section of the assignment covers project management with a focus on network development and crashing. The project parameters are:

Project Parameters

Task

Length

(weeks)

Immediate Predecessors

Crash Cost per week

Maximum weeks crashed

A

7

$200

1

B

10

$250

3

C

6

A

$250

1

D

6

A

$300

1

E

1

B

-

0

F

1

C,D

-

0

G

3

D, E

$200

2

H

3

F

$350

1

I

2

G

-

0

a) You are asked to shorten the project by three weeks. If you shorten it by three weeks you will be given a bonus of $1,000. After you shorten the project by one week, is there more than one critical path? Yes or No.

b) You are asked to shorten the project by three weeks. If you shorten it by three weeks you will be given a bonus of $1,000. After you shorten the project by two weeks, is there more than one critical path? Yes or No.

c) You are asked to shorten the project by three weeks. If you shorten it by three weeks you will be given a bonus of $1,000. After you shorten the project by three weeks, what is the earliest finish time of activity I?

d) You are asked to shorten the project by three weeks. If you shorten it by three weeks you will be given a bonus of $1,000. After you shorten the project by three weeks, what is the slack time in activity H?

e) You are asked to shorten the project by three weeks. If you shorten it by three weeks you will be given a bonus of $1,000. After you shorten the project by three weeks, what is your minimum cost to shorten it?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!