This single line diagram shows the existing 132kV transmission network from Power Station C to Substation SS
Fantastic news! We've Found the answer you've been seeking!
Question:
This single line diagram shows the existing 132kV transmission network from Power Station C to
Substation SS with supply of 60A, to Substation ST with supply of 120A, and to Substation KT
with supply of 200A. Length of OverHead Line (OHL) between Power Station C and Substation
SS is 40km, between Substation SS and ST is 10km, and between ST and KT is 20km. OHL
resistance is 0.01 ohm per kilo-metre.
1)What if we link up Power Station C and substation KT with same OHL and 30km in length?
2)What are the advantages and disadvantages of Ring Connected Power Grid? (Hints : Contrast the efficiency before and after link up C-KT)