Question: This unit examines the project management execution process focusing on scheduling, resources, and cost. Given all the estimating done to determine the duration of project
This unit examines the project management execution process focusing on scheduling, resources, and cost. Given all the estimating done to determine the duration of project activities, explain what it means to say that only after the fact do we know which path the critical path was actually? Provide an example or two of how such statement might manifest itself in a real project?