Question: Thomas Landscaping plants grass seed as the basic landscaping for business campuses. During a recent month, the company worked on three projects (Remington, Chang, and

Thomas Landscaping plants grass seed as the basic landscaping for business campuses. During a recent month, the company worked on three projects (Remington, Chang, and Wyco). The company is interested in controlling the materials costs, namely the grass seed, for these plantings projects. In order to provide management with useful cost control information, the company uses standard costs and prepares monthly variance reports. Analysis reveals that the purchasing agent mistakenly purchased poor-quality seed for the Remington project. The Chang project, however, received higher-than-standard-quality seed that was on sale. The Wyco project received standard-quality seed. However, the price had increased and a new employee was used to spread the seed. Shown below are quantity and cost data for each project.

Actual

Standard

Project

Quantity

Costs

Quantity

Costs

Total Variance

Remington

520 lbs. $1,248 450 lbs. $1,170 $78 U

Chang

400 920 410 1,066 146 F

Wyco

620 1,674 550 1,430 244 U

Total variance

$176 U

(a) Prepare a variance report for the purchasing department. (Round actual and standard price per pound answers to 2 decimal places e.g. 1.25.)Thomas Landscaping plants grass seed as the basic landscaping for business campuses. During a recent month, the company worked on three projects (Remington, Chang, and Wyco). The company is interested in controlling the materials costs, namely the grass seed, for these plantings projects. In order to provide management with useful cost control information, the company uses standard costs and prepares monthly variance reports. Analysis reveals that the purchasing agent mistakenly purchased poor-quality seed for the Remington project. The Chang project, however, received higher-than-standard-quality seed that was on sale. The Wyco project received standard-quality seed. However, the price had increased and a new employee was used to spread the seed. Shown below are quantity and cost data for each project.

Actual

Standard

Project

Quantity

Costs

Quantity

Costs

Total Variance

Remington

520 lbs. $1,248 450 lbs. $1,170 $78 U

Chang

400 920 410 1,066 146 F

Wyco

620 1,674 550 1,430 244 U

Total variance

$176 U

(a) Prepare a variance report for the purchasing department. (Round actual and standard price per pound answers to 2 decimal places e.g. 1.25.)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock