Question: ( Thomas Lee Project Management Proposal ) Thomas Lee, the project manager of a task force planning the construction of a domed stadium had hoped

(Thomas Lee Project Management Proposal) Thomas Lee, the
project manager of a task force planning the construction of a domed
stadium had hoped to be able to complete construction prior to the start of
the next college football season. He and his team have almost finished
developing the proposal that will be presented to a management committee
for approval. All that remains to be done is to develop a time estimate for the
project. Toward that end, a network diagram has been developed. The
network diagram has two paths with expected completion times and standard
deviations, as shown in the following table. Estimate the number of days
required to complete the project with probability 0.95(round your answer to
two decimal places).
Path .Expected Duration (Days) Standard Deviation
A .69.9
B .65.13

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!