Question: Thomas needs to send information about project's progress to his stakeholders. It is not confirmed by any of them that they have received the information,
Thomas needs to send information about project's progress to his stakeholders. It is not confirmed by any of them that they have received the information, or understood. This type of communication is known as:
Step by Step Solution
There are 3 Steps involved in it
The detailed answer for the above question is provided below The answer is c Push commu... View full answer