Question: Three cost estimates were $ 9 , 0 0 0 . 0 0 , $ 4 , 0 0 0 . 0 0 , and

Three cost estimates were $9,000.00, $4,000.00, and $15,000.00, not given in any order. What is the PERT? (Hint: optimistic is whatever the smallest estimate is, pessimistic is the largest number, and the third number is most likely) Pick closest answer