Question: Three masons and two helpers work together to build 5 0 0 sq . ft . wall using 8 ' ' 8 ' ' 1

Three masons and two helpers work together to build 500 sq. ft . wall using 8''8''16'' concrete masonry units. The production rate is 0.11 work hours per square foot for this crew. Masons work 65% of total hours and helpers work 35% of total hours. Burdened Wage rates are $33 per hour for masons and $23 per hour for helpers. What is the closest total labor cost for this project?
Three masons and two helpers work together to