Question: Three programming activities must be completed on time, in order, to begin testing on time. The first two activities have a 90% probability of being
Three programming activities must be completed on time, in order, to begin testing on time. The first two activities have a 90% probability of being completed by the due date. The third has an 80% probability of being completed on time. What is the probability of starting the testing on time? Question 9 options: 72 % 87 % 65 % 70 %