Question: Three standard procedures for closing projects include _________. Question 16Answer a. Procurement closeout, administrative closeout, and variability closeout b. Administrative closeout, documenting lessons learned, and
Three standard procedures for closing projects include _________. Question 16Answer a. Procurement closeout, administrative closeout, and variability closeout b. Administrative closeout, documenting lessons learned, and procurement closeout c. Documenting lessons learned, variability review, and contractor feedback d. Variability review, administrative closeout, and contractor feedback