Question: Throughout development, what role does conducting test and evaluation play in mitigating project risk? Question 2 5 Select one: A . Identifying system performance failures

Throughout development, what role does conducting test and evaluation play in mitigating project risk?
Question 25Select one:
A.
Identifying system performance failures earlier, when it costs less to correct them
B.
Identifying project team member performance issues
C.
Supporting requests for more funding from the customer
D.
Providing research data for future projects