Question: Throughput Costing and Decision Making in a Constrained Environment : A manufacturing company produces two products, X and Y, using a common bottleneck machine. The
Throughput Costing and Decision Making in a Constrained Environment: A manufacturing company produces two products, X and Y, using a common bottleneck machine. The bottleneck machine has a capacity of 1,000 hours per month. Product X requires 2 hours of machine time and sells for $150 with variable costs of $50. Product Y requires 3 hours of machine time and sells for $200 with variable costs of $80. Determine which product the company should prioritize to maximize throughput contribution, considering the limited machine hours.