Question: thumbs up for full answer 7. [15 points] An assembly line with 30 activities is to be balanced. The total amount of time to complete
7. [15 points] An assembly line with 30 activities is to be balanced. The total amount of time to complete all 30 activities is 60 minutes. The longest activity takes 2.4 minutes and the shortest takes. 3 minutes. The line will operate for 480 minutes per day. The line is balanced using 14 workstations and a finished product can be produced every 4.5 minutes. a. What are the maximum and minimum cycle times? b. How much daily output will be achieved by each of those cycle times? c. What is the production rate in units per day? d. What is the assembly line efficiency
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts