Question: Time 5. Given the following time chart: Activity Immediato Optimistic Most Predecessor Likely (Hr.) Time (Hr.) A 3 B 2 2 3 3 D 5

Time 5. Given the following time chart: Activity
Time 5. Given the following time chart: Activity Immediato Optimistic Most Predecessor Likely (Hr.) Time (Hr.) A 3 B 2 2 3 3 D 5 E B 5 F 5 G E.F H D 1 G.H 3 Find out the following: Pessimistic Time (Hr) 11 2 9 7 5 B 3 5 Expected time for each activity. Variance for cach activity Critical path. Total project completion time. Variance in completion time for the critical path

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!