Question: TIME ( DAYS ) ACTIVITY a m b IMMEDIATE PREDECESSOR ( S ) A 3 6 8 B 2 4 4 C 1 2 3
TIME DAYS ACTIVITY a m b IMMEDIATE PREDECESSORS A B C D C E B D F A E G A E H F I G J C K H I a Determine the expected completion time and variance for each activity. b Determine the total project completion time and the critical path for the project. c Determine ES EF LS LF and slack for each activity. d What is the probability that Kelle Carpet and Trim will finish the project in days or less?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
