Question: TIME ( DAYS ) ACTIVITY a m b IMMEDIATE PREDECESSOR ( S ) A 3 6 8 B 2 4 4 C 1 2 3

TIME (DAYS) ACTIVITY a m b IMMEDIATE PREDECESSOR(S) A 368 B 244 C 123 D 678 C E 246 B, D F 61014 A, E G 124 A, E H 369 F I 101112 G J 141620 C K 2810 H, I a) Determine the expected completion time and variance for each activity. b) Determine the total project completion time and the critical path for the project. c) Determine ES, EF, LS, LF, and slack for each activity. d) What is the probability that Kelle Carpet and Trim will finish the project in 40 days or less?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!