Question: Time ( days ) Immediate Time ( days ) Immediate Activity a m b Predecessor ( s ) Activity a m b Predecessor ( s

Time(days)
Immediate
Time(days)
Immediate
Activity
a
m
b
Predecessor(s)
Activity
a
m
b
Predecessor(s)
A
4
6
7
long dash
H
4
4
6
E, F
B
1
2
3
long dash
I
1
6
8
G, H
C
6
6
6
A
J
2
5
7
I
D
5
8
11
A
K
8
9
11
I
E
1
9
18
B, C
L
2
4
6
J
F
2
3
6
D
M
1
2
3
K
G
1
7
8
D
N
6
8
10
L, M
Part 2
a) The expected completion time of the project=
enter your response here days (round your response to two decimal places).
Part 3
The activities that represent the project's critical path are
A - C - E - H - I - K - M - N
B - E - H - I - J - L - N
B - E - H - I - K - M - N
A - D - F - H - I - K - M - N
A - D - F - H - I - J - L - N
A - C - E - H - I - J - L - N
A - D - G - I - J - L - N
A - D - G - I - K - M - N
.
Part 4
b) If the time to complete the activities on the critical path is normally distributed, then the probability that the critical path will be finished in 53 days or less=
enter your response here (round your response to two decimal places).
Part 5
c) Using the standard normal tableLOADING..., the number of days that would result in99% probability of completion=
enter your response here days (round your response to two decimal places).

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!