Question: TIME (DAYS) o ACTIVITY m b IMMEDIATE PREDECESSOR(S) A 6 8 3 2 B 4 2 1 6 3 8 7 Considering the following information

TIME (DAYS) o ACTIVITY m b IMMEDIATE
TIME (DAYS) o ACTIVITY m b IMMEDIATE PREDECESSOR(S) A 6 8 3 2 B 4 2 1 6 3 8 7 Considering the following information about a project: 1- Determine the expected completion time and variance for each activity 2- Determine the total project completion time and critical path for the project 3- What is the probability that the project will be finished within 40 days? D E 2 4 6 F 6 10 14 4 B, D . 1 G Z 6 3 9 10 14 11 16 8 12 20 G HI K 2 10