Question: Time Estimates (week) Most Immediate Activity Optimistic Likely Pessimistic Predecessor(s) A 1 4 7 B 2 6 10 C 3 3 9 3 C D

Time Estimates (week) Most Immediate Activity Optimistic Likely Pessimistic Predecessor(s) A 1 4 7 B 2 6 10 C 3 3 9 3 C D 6 13 E 4 6 14 14 16 AC F 6 8 B G 2 5 8 D, E, F a. Calculate the expected activity times (round to nearest integer) b. Calculate the activity slacks. What is the total project length? Make sure you fully label all nodes in the network. c. Identify the critical path. What are the alternative paths, and how much slack time is associated with each non- critical path? d. Identify the burst activities and the merge activities. e. Given the activity variances, what is the likelihood of the project finishing on week 24? f. Suppose you wanted to have 99% confidence in the project finishing on time. How many additional weeks would your project team need to negotiate for in order to gain this 99% likelihood? ho
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock