Question: time ( in days ) and those activities that lie along the critical path. The appropriate data are shown in the following table: table

time (in days) and those activities that lie along the critical path. The appropriate data are shown in the following table:
\table[[Activity,Time (days),\table[[Immediate],[Predecessor(s)]],Activity,Time (days),\table[[Immediate],[Predecessor(s)]]],[a,m,b,a,m,b],[A,5,6,8,Predeces,H,3,3,8,E, F],[B,1,3,3,,I,1,5,8,G, H],[C,5,5,5,A,J,1,4,7,I],[D,5,9,11,A,K,7,8,12,I],[E,3,9,18,B, C,L,2,4,8,J],[F,3,3,6,D,M,1,3,5,K],[G,2,6,10,D,N,6,7,12,L, M]]
a) The expected completion time of the project = days (round your response to two decimal places).
time ( in days ) and those activities that lie

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!