Question: Time left 0 : 0 0 : 5 0 a . A bottling plant fills 3 , 9 6 0 bottles every three hours (
Time left ::
a A bottling plant fills bottles every three hours or per minute The lead time is minutes, and a container accommodates bottles. The safety stock is percent of the expected demand.
How many kanban card sets are needed round up to the nearest kanban card
b Arrow Distributing Corp likes to track inventory by using weeks of supply as well as by inventory tumover. The following information is from its latest financial report: