If a project has a Schedule Performance Index (SPI) of 0.90, this means that:
Question 15Answer
a.
90% of the budget plannedto datehas been spent
b.
90% of the work of the whole project has been completed
c.
90% of the work planned to datehas beencompleted
d.
90% of the project budget has beenspent