A farmer has identified seven tasks and developed three time estimates (all in days) of the next big project on the farm, replacing the fence at the comedy pasture. Tasks, precedence requirements, and time estimates are shown in the table. What is the late finish for the Plant Posts activity?
Activity
Optimistic time
Most Likely time
Pessimistic time
Predecessor
Corner Posts
4
5
6
--
String Line
7
8
9
--
Dig Holes
10
12
14
Corner Posts
Plant Posts
11
14
17
String Line
Weld Top Bar
8
11
14
String Line
Paint
9
11
13
Dig Holes, Plant Posts
Tack Wire
9
12
16
Weld Top Bar
Question 66Select one:
a.
20.83 days
b.
8 days
c.
13.3 days
d.
22 days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!