Question: Time left 0 : 1 6 : 1 3 Question 9 Not yet answered Marked out of 8 . 0 0 Flag question Question text

Time left 0:16:13
Question 9
Not yet answered
Marked out of 8.00
Flag question
Question text
Sydney Manufacturing produces custom-built pollution control devices fro medium-size steel mills. The most recent project undertaken by the manager requires 6 different activities. The appropriate data is shown in the following (a=Optimistic, m=most likely, b= pessimistic times). Assume that the activity times are independent:
Activity
Immediate predecessors(s)
a
m
b
A
-
2
4
6
B
-
1
2
3
C
-
6
6
6
D
A,B
5
8
11
E
C
1
9
17
F
D,E
2
3
4
a) Determine the total expected project completion time.
b) How much is the Variance of the project?
Select one:
a)13 days; b)4.43
a)18 days; b)7.22
a)13 days; b)3.55
a)18 days; b)6.5

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!