Sydney Manufacturing produces custombuilt pollution control devices fro mediumsize steel mills. The most recent project undertaken by the manager requires different activities. The appropriate data is shown in the following aOptimistic, mmost likely, b pessimistic times Assume that the activity times are independent:
Activity
Immediate predecessorss
a
m
b
A
B
C
D
AB
E
C
F
DE
a Determine the total expected project completion time.
b How much is the Variance of the project?
Select one:
a days; b
a days; b
a days; b
a days; b