Question: Time left 0 : 2 3 : 3 0 cards to authorize production and movement of materials in a new process. The average of 9

Time left 0:23:30
cards to authorize production and movement of materials in a new process. The average of 90 minutes to complete a pieces of a part per hour. Each container holds 46 pieces. A Kanban will take an many Kanbans are needed to ensure the demand is mecess is new, the manager has assigned a safety factor of 0.8. How
3 Kanbans
4 Kanbans
5 Kanbans
6 Kanbans
 Time left 0:23:30 cards to authorize production and movement of materials