Question: Time left 0 : 2 6 : 1 3 Question 5 0 Not yet answered Marked out of 5 Flag question Question text * *
Time left ::
Question
Not yet answered
Marked out of
Flag question
Question text
This question is worth marks
A project has the activity duration and cost information indicated in the table where all times are in weeks. For every week longer than weeks, there is a penalty of $ By balancing the cost of penalty against the crash costs of the activities, what is the total crashed cost for completing this project?
Activity
Normal time
Crash time
Normal Cost
Crash Cost
Predecessor
A
$
B
A
C
A
D
B
E
B
F
C D
G
E F
Question Select one:
a
$
b
$
c
$
d
$
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
