Question: Time left 0 : 2 6 : 1 3 Question 5 0 Not yet answered Marked out of 5 Flag question Question text * *

Time left 0:26:13
Question 50
Not yet answered
Marked out of 5
Flag question
Question text
** This question is worth 5 marks **
A project has the activity duration and cost information indicated in the table where all times are in weeks. For every week longer than 30 weeks, there is a penalty of $300. By balancing the cost of penalty against the crash costs of the activities, what is the total crashed cost for completing this project?
Activity
Normal time
Crash time
Normal Cost
Crash Cost
Predecessor
A
8
5
$1,000
2,000
B
6
4
1,500
2,000
A
C
8
5
1,800
2,300
A
D
12
9
1,000
1,800
B
E
14
11
950
1,450
B
F
9
7
1,500
1,900
C, D
G
7
5
2,300
2,800
E, F
Question 50Select one:
a.
$13,550
b.
$14,250
c.
$13,950
d.
$13,150

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!