The project sponsor has approached you with a dilemma. The CEO announced at the annual stockholders meeting that the project youre managing will be completed by the end of this year. The problem is that this is six months prior to the scheduled completion date. Its too late to go back and correct her mistake, and stockholders are expecting implementation by the announced date. You must speed up the delivery date of this project. Your primary constraint before this occurred was the budget. What actions can you take to help speed up the project?
Question Answer
a
Examine the project plan to see whether there are any phases that can be fast tracked and then revise the project plan to reflect the compression of the schedule.
b
Utilize negotiation and influencing skills to convince the project sponsor to speak with the CEO and make a correction to her announcement.
c
Ask for more money so that you can contract out one of the phases you had planned to do with inhouse resources.
d
Hire more resources to get the work completed faster
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock