Question: Time left 0 : 3 6 : 4 9 You have a project with the following activities: Activity A takes 4 0 hours and can
Time left ::
You have a project with the following activities: Activity A takes hours and can start after the project starts. Activity B takes hours and should happen after Activity A Activity must happen after activity and takes hours. Activity D must happen after activities and takes hours.
Activity must take place after activity and takes hours. Activity takes place after Activity and takes hours. Activity takes places after Activities and D Activity is the last activity of the project and take hours. Which of the following is true if Activity Ds duration actually takes hours?
a The critical path increases by hours.
b The critical path is hours.
c The critical path changes to A B D G
d Tie critical path remains A B C E F G
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock