Question: Time left 0 : 4 1 : 3 3 An organization has a project management office ( PMO ) that ensures all relevant project documents
Time left ::
An organization has a project management office PMO that ensures all relevant project documents are created, and all project management processes are followed according to established best practices. What should the project manager review first to identify stakeholders for a newly started project?
The communication plan is to learn about the project stakeholder's
The stakeholder engagement plan identifies the management strategies and actions required to engage stakeholders
The business documents as a source of information about the project's stakeholders