Question: Time left 0 : 4 5 : 2 9 Question 1 Not yet answered Marked out of 6 . 0 0 Flag question Question text

Time left 0:45:29
Question 1
Not yet answered
Marked out of 6.00
Flag question
Question text
Decision Tree Analysis. You are considering the decision to purchase a machine for internal production or to subcontract the work to an external source. The following information has been provided by your financial managers:
Cost to purchase the machine$35,000
Cost to subcontract the work$5,000
Probability of a good market =70%
Probability of a poor market =30%
Reward if the prediction occurs:
In the purchase machine decision good market scenario$80,000;
in the poor market scenario$30,000
In the Subcontract decision good market scenario$50,000; in the poor market scenario$15,000
1. What is the expected value of the decision to purchase the machine? Answer Question 1
Purchase$29,999.99. Subcontract$34,500.00
Question 2
Answer saved
Marked out of 1.00
Flag question
Question text
You are the project manager for the KOY Project. This project requires quality that maps to federal guidelines. During a quality audit, you discovered that a portion of the project work is faulty and must be done again. The requirement to do the work is an example of which of the following?
Question 2Answer
a.
Cost of adherence
b.
Cost of doing business
c.
Cost of nonconformance
d.
Cost of quality
Question 3
Answer saved
Marked out of 1.00
Flag question
Question text
You are the project manager for a large manufacturer of wood furniture. Your new project is the Shop Table Project, which will be the creation and manufacturing of a new table for woodworkers to use in their wood shops. On this project you have elected to use JIT for scheduling. Which of the following is an advantage to using JIT?
Question 3Answer
a.
Decreases the inventory investment.
b.
Allows for a broad range of deviation than other inventory solutions.
c.
Requires materials to be readily available.
d.
Allows the project team to have control over the materials.
Question 4
Answer saved
Marked out of 1.00
Flag question
Question text
Mark is the project manager of the PMH Project. Quality audits of the deliverables show there are several problems. Management has asked Mark to create a chart showing the distribution of problems and their frequencies. Management wants which of the following?
Question 4Answer
a.
Control chart
b.
Pareto diagram
c.
Ishikawa chart
d.
Flow chart
Question 5
Not yet answered
Marked out of 3.00
Flag question
Question text
Match each type of conflict management technique with the appropriate definition
Forcing
Answer 1 Question 5
Choose...
Smoothing /Accommodating
Answer 2 Question 5
Incorporating multiple viewpoints and achieving consensus
Collaborating
Answer 3 Question 5
Choose...
Withdrawing /avoiding
Answer 4 Question 5
Offers only win / lose solutions
Compromising
Answer 5 Question 5
Emphasize areas of agreement instead of areas of disagreement
Confronting / Problem Solving

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!