Question: Time left 0 : 4 7 : 5 0 Question 6 5 Answer saved Marked out of 1 . 0 Flag question Question text Use

Time left 0:47:50
Question 65
Answer saved
Marked out of 1.0
Flag question
Question text
Use the information contained below to calculate the total normal cost of the project.
Activity
ID Slope Max crash
time Normal
Time Normal
Cost Crash
Time Crash
Cost
A $8028 $406 $200
B $2025 $803 $120
C $50212 $5010 $150
D $100114 $10013 $200
E $4014 $603 $100
F $003 $1833 $183
Answer:
513
Question 66
Not yet answered
Marked out of 1.0
Flag question
Question text
You plan to compress the schedule using a one-time unit per move and the least cost method.
You want to reduce the schedule until you reach the maximum crash point (crash duration) of the network.
You have already identified which activities to crash and the crashing order of these activities to reach the crash point.
The crashing order is the following:
Iteration 1- activity B
Iteration 2- activity B
Iteration 3- activity E
Iteration 4- activity C
Iteration 5- activity D
What will the total cost of the project be after iteration 1?
You can use the Excel file Q66-Schedule Crashing as a helping tool. No need to upload the solution in Excel.
Answer:
Question 67
Not yet answered
Marked out of 1.0
Flag question
Question text
What will the cost of the project be after iteration 2?
Answer:
Question 68
Not yet answered
Marked out of 1.0
Flag question
Question text
What will the cost of the project be after iteration 3?
Answer:
Question 69
Not yet answered
Marked out of 1.0
Flag question
Question text
What will the cost of the project be after iteration 4?
Answer:
Question 70
Not yet answered
Marked out of 1.0
Flag question
Question text
What will the cost of the project be after iteration 5?
Answer:
Question 71
Not yet answered
Marked out of 1.0
Flag question
Question text
What is the project duration at the crash point?
a.
20 weeks
b.
24 weeks
c.
22 weeks
d.
23 weeks
e.
21 week

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!