Question: Time left 1 : 1 3 : 0 1 Information Not flaggedFlag question Information text Use the following information to compress one time unit per

Time left 1:13:01
Information
Not flaggedFlag question
Information text
Use the following information to compress one time unit per move using the least-cost method.
The indirect costs for each duration are $500 for 12 days, $400 for 11 days, $300 for 10days, $200 for 9 days, $100 for 8 days.
The Crash Cost per unit time (Slope) is already given and the Maximum crash time is given. Theres no need to calculate.
Crash
Question 1
Answer saved
Marked out of 3.00
Not flaggedFlag question
Question text
Use the table above to answer the following:
For a time duration of 12 days, what is the total direct, total indirect, and TOTAL project costs.
Please note: you have to give 3 answers (total direct, total indirect, and TOTAL project) to gain the full marks.
Direct Cost: $2050
Indirect Cost: $500
Total Cost: $2550
$2600 $450 $2110 $300 $600 $400 $2000 $2300 $2500
Question 2
Answer saved
Marked out of 3.00
Not flaggedFlag question
Question text
Use the table above to answer the following:
For a time duration of 11 days, what is the total direct, total indirect, and TOTAL project costs.
Please note: you have to give 3 answers (total direct, total indirect, and TOTAL project) to gain the full marks.
Direct Cost: $2110
Indirect Cost: $400
Total Cost: $2300
$200 $700 $100 $2050 $2450 $300 $2410 $2400 $2370 $2170
Question 3
Not yet answered
Marked out of 3.00
Not flaggedFlag question
Question text
Use the table above to answer the following:
For a time duration of 10 days, what is the total direct, total indirect, and TOTAL project costs.
Please note: you have to give 3 answers (total direct, total indirect, and TOTAL project) to gain the full marks.
Direct Cost: $2170
Indirect Cost: $200
Total Cost: $2370
$2410 $500 $400 $2500 $2300 $2110 $300 $2450 $2000 $2050
Question 4
Not yet answered
Marked out of 3.00
Not flaggedFlag question
Question text
Use the table above to answer the following:
For a time duration of 9 days, what is the total direct, total indirect, and TOTAL project costs.
Please note: you have to give 3 answers (total direct, total indirect, and TOTAL project) to gain the full marks.
Direct Cost: blank
Indirect Cost: blank
Total Cost: blank
$2000 $2170 $2110 $200 $2370 $400 $500 $2500 $2450 $100 $2300 $2400 $2050

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!