Question: Time left 1 : 1 4 : 2 6 On April 1 , KO Contractors, Inc., contracts to build a store for Lo - Cost

Time left 1:14:26
On April 1, KO Contractors, Inc., contracts to build a store for Lo-Cost Housewares at a specific location in Metro City. On May 1, M changes its zoning law to prohibit the construction of a commercial building at that location. Lo-Cost Housewares files a suit again Contractors. In this situation
Select one:
KO is in breach of contract.
Lo-Cost is in breach of contract.
the contract is discharged.
the contract is suspended.
Time left 1 : 1 4 : 2 6 On April 1 , KO