Question: Time lett 0 . 2 9 , 4 8 Annual demand for a new assembled product is expected to be 7 5 , 0 0

Time lett 0.29,48
Annual demand for a new assembled product is expected to be 75,000 units. Work content time for the product is 258 min The assemby line works 50 wk/yr,40hrwk. Expected line efficiency is 95%. With one worker per station, determine ideal minimum rumber of workers
a.17
b.19
c.21
d.15