Activity Precedent Duration ES EF
A None 7 0 7
B A 10 7 17
C A 6 7 13
D C 15 13 28
E B 9
F D & E 6
G F & D 10
H E & D 15
I E, G, H 2
J G & H 5
K I & J 5
USE THE FOLLOWING FORMAT FOR YOUR NETWORK ITEMS; BE NEAT OR NO PARTIAL CREDIT WILL BE AWARDED.
| ES | DUR | EF |
| ACTIVITY | ||
| LS | FLOAT | LF |
The float in the above format chart is for total float. Free float to be shown on network.