Question: Time Management Problem (70 Total Points) 1. Network by Node (20 Pts) 2. Find Total Float Using Node Network (20 Pts) 3. Highlight the Critical

Time Management Problem (70 Total Points)

1. Network by Node (20 Pts)

2. Find Total Float Using Node Network (20 Pts)

3. Highlight the Critical Path (5 Pts)

Activity Precedent Duration ES EF

A None 7 0 7

B A 10 7 17

C A 6 7 13

D C 15 13 28

E B 9

F D & E 6

G F & D 10

H E & D 15

I E, G, H 2

J G & H 5

K I & J 5

USE THE FOLLOWING FORMAT FOR YOUR NETWORK ITEMS; BE NEAT OR NO PARTIAL CREDIT WILL BE AWARDED.

ES

DUR

EF

ACTIVITY

LS

FLOAT

LF

The float in the above format chart is for total float. Free float to be shown on network.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!