Question: Time (weeks) Immediate Time (weeks) Immediate Activity a m b Predecessor(s) Activity a m b Predecessor(s) A 4 8 10 G 3 3 5 C,

Time

(weeks)

Immediate

Time

(weeks)

Immediate

Activity

a

m

b

Predecessor(s)

Activity

a

m

b

Predecessor(s)

A

4

8

10

G

3

3

5

C, E

B

1

8

23

A

H

2

2

2

F

C

8

14

16

A

I

5

5

5

F

D

5

6

9

A

J

4

7

12

D, G, H

E

1

3

4

B

K

3

3

4

I, J

F

5

9

21

C, E

a) The expected (estimated) time for activity C is

13.3313.33

weeks. (Round your response to two decimal places.)

b) The variance for activity C is

1.331.33

weeks. (Round your response to two decimal places.)

c) Based on the calculation of the estimated times, the critical path is

A - C - F - H - J - K

.

NEED ANSWERED

d. what is the estimated time of the critical path?

e. what is the activity variance along the critical path?

f. what is the probability of completion of the project before week 36?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!