Question: Timeline Project Stage Start Finish Duration 1. Internal Analysis January March 60 days 2. System Configuration April May 40 days 3. Data Preparation and Cleansing
- Timeline
| Project Stage | Start | Finish | Duration |
| 1. Internal Analysis | January | March | 60 days |
| 2. System Configuration | April | May | 40 days |
| 3. Data Preparation and Cleansing | June | October | 100 days |
| 4. Development | August | September | 30 days |
| 5. Testing | September | October | 30 days |
| 6. Training and Support | October | November | 20 days |
| 7. Go Live Activities | November | December | 20 days |
| 8. Close Down and Review | December | January | 20 days |
|
|
|
|
| ||
|---|---|---|---|---|---|---|
|
|
|
| |||
| 1. | Internal Analysis | |||||
| 1.1 | User processes | Project approval | 15 | Business analyst | N/A | Process writing software |
| 1.2 | Identify data requirements | Develop an overview of user processes | 15 | Business analyst | N/A | Data collection tools |
| 1.3 | Analyse stakeholder needs | Identify data requirements | 15 | Business analyst | N/A | Stakeholder analysis tools |
| 1.4 | Review current business processes | Analyse stakeholder needs | 15 | Business analyst, Operations Manager | N/A | Process review tools |
| 2 | System Configuration | |||||
| 2.1 | Software purchase | Project approval | 1 | IT Manager | N/A | N/A |
| 2.2 | Determine hardware requirements | Purchase Sage CRM | 5 | IT Manager | N/A | N/A |
| 2.3 | Obtain hardware and peripherals | Determine hardware requirements | 10 | IT Manager | Hardware | N/A |
| 2.4 | Determine customisation requirements | Obtain hardware and peripherals | 10 | IT Manager, Business Analyst | N/A | N/A |
| 2.5 | Approve and finalise customisation specifications | Determine customisation requirements | 14 | IT Manager, Review team | N/A | N/A |
| 3 | Data preparation and cleansing | |||||
| 3.1 | Review and clean data | Approve and finalise customisation specifications | 100 | Data analysts | N/A | Data cleansing tools |
| 4 | Development | |||||
| 4.1 | Determine security roles | Review and clean data | 5 | Development team | N/A | N/A |
| 4.2 | Complete system configuration | Determine security roles | 5 | Development team | N/A | Configuration tools |
| 4.3 | Finalise customisation code | Complete system configuration | 5 | Development team | N/A | Development tools |
| 4.4 | Conduct acceptance testing | Finalise customisation code | 5 | QA team | Testing scripts | Testing environment |
| 4.5 | Begin developing data migration scripts | Conduct acceptance testing | 5 | Data Analyst, IT Developer | Migration scripts | Development tools |
| 4.6 | Configure system settings | Begin developing data migration scripts | 5 | IT Developer | N/A | Configuration tools |
| 5 | Testing | |||||
| 5.1 | Conduct infrastructure testing | Configure system settings | 6 | Testing team | N/A | Testing environment |
| 5.2 | Conduct system testing | Conduct infrastructure testing | 6 | Testing team | N/A | Testing environment |
| 5.3 | Conduct user acceptance testing (UAT) | Conduct system testing | 6 | Testing team, Users | N/A | Testing environment |
| 5.4 | Conduct pilot group testing | Conduct user acceptance testing (UAT) | 6 | Testing team, Pilot group | N/A | Testing environment |
| 5.5 | Finish customisation | Conduct pilot group testing | 6 | Development team | Customisation specifications | Development tools |
| 6 | Training and support | |||||
| 6.1 | Administrator training | Development | 4 | Training manager and consultants | Training materials | Sage CRM |
| 6.2 | Schedule and deliver user training | Schedule and deliver administrator training | 4 | Training manager, Consultants | Training materials | Sage CRM |
| 6.3 | Develop process flows for CRM use | Schedule and deliver user training | 4 | Business Analyst | Process flow templates | N/A |
| 6.4 | Develop specific user policies and procedures | Develop process flows for CRM use | 4 | Policy Writer | Policy templates | N/A |
| 6.5 | Develop quick help guides | Develop specific user policies and procedures | 4 | Documentation Specialist | Guide templates | N/A |
| 7 | Go Live | |||||
| 7.1 | Migrate data | Provide ongoing help desk support | 10 | Data Analyst, IT Developer | Migration scripts | Development tools |
| 7.2 | Release final deliverables | Migrate data | 10 | Project Manager, IT Manager | N/A | Release tools |
| 8 | Close down and review | |||||
| 8.1 | Conduct technical support handover | Release final deliverables | 4 | IT Manager, Support Team | Handover documentation | N/A |
| 8.2 | Conduct post-implementation review | Conduct technical support handover | 4 | Project Manager, Key Stakeholders | Review templates | N/A |
| 8.3 | Review final communication plan | Conduct post-implementation review | 3 | Communication Manager | Communication plan | N/A |
| 8.4 | Produce end of project report | Review final communication plan | 3 | Project Manager | Report templates | N/A |
| 8.5 | Perform change management review | Produce end of project report | 3 | Change Manager | Review templates | N/A |
| 8.6 | Ensure all required documentation is distributed | Perform change management review | 3 | Project Manager | Documentation | N/A |
Develop the project schedule using appropriate software and techniques. It is recommended that you use a simple Gantt Chart
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock