Question: Times Costs Per Day Activities IPs Normal Crash Normal Crash A -- 2 1 5 15 B -- 8 6 22 30 C A 3
| Times | Costs | Per Day | ||||
| Activities | IPs | Normal | Crash | Normal | Crash | |
| A | -- | 2 | 1 | 5 | 15 | |
| B | -- | 8 | 6 | 22 | 30 | |
| C | A | 3 | 2 | 10 | 13 | |
| D | C | 2 | 1 | 11 | 17 | |
| E | C | 10 | 6 | 20 | 40 | |
| F | B,C | 4 | 3 | 8 | 15 | |
| G | D | 4 | 3 | 9 | 10 | |
| H | E,F | 1 | 1 | 10 | 10 | |
| I | E,G | 3 | 2 | 8 | 10 | |
| J | H,I | 2 | 1 | 17 | 20 | |
Use the above information to 1. Draw a network diagram and find the critical path 2. Identify they nodes with slack and the amount 3. Reduce the project by 5 days 4. Show the order and extra cost of reducing the project 5.. (HINT: for the variability, you only need the variability of those activities on the critical path.)
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock