Question: TIMES (DAYS) IMMEDIATE ACTIVITY PREDECESSORS Expected Time Variance a m b A 1 3 5 3 0.44 B 1 2 3 2 0.11 C 1

TIMES (DAYS) IMMEDIATE ACTIVITY PREDECESSORS Expected Time Variance a m b A 1 3 5 3 0.44 B 1 2 3 2 0.11 C 1 2 3 2 0.11 D A 2 3 4 3 0.11 E B. 3 4 11 5 1.78 F C D 3 4 5 4 0.11 G DE 5 7 19 7 0.44 H F, G 3 5 7 5 0.44 C (2) F (4) A(3) H (5) D (3) G() B (2) E (5) What is the expected project completion time? 21 O 19 O 18 0 17 O 15