Question: tion 2 yet wered Consider the activities, durations, and predecessor relationships in the following network. Draw the network and answer the questions that follow. Immediate

tion 2 yet wered Consider the activities,

tion 2 yet wered Consider the activities, durations, and predecessor relationships in the following network. Draw the network and answer the questions that follow. Immediate Optimistic Most Likely Activity Pessimistic Description Predecessor(s) (Weeks) (Weeks) (Weeks) ked out of Flag question A 4 7 10 B A 2 8 C A 8 12 16 D B 1 2. 3 E D C 6 8 22 og som N Nam F 2 3 4 G F 2 2 2 H F 6 8 10 1 E, G, H 4 8 12 1 1 2 What is the variance for activity B

Step by Step Solution

There are 3 Steps involved in it