Question: TO 3 . EO 3 b Given a DoD acquisition scenario, determine the applicability of contract administration po Question 6 of 2 4 . You
TOEOb Given a DoD acquisition scenario, determine the applicability of contract administration po
Question of
You have just been informed that a purchase order you recently awarded for noncommercial supplies is no longer needed and must be cancelled. The order was accepted in writing by the contractor. Which one of the following statements is true?
The purchase order is considered cancelled once the contracting officer verifies the contractor has received the Government's written cancellation.
The purchase order is considered cancelled if the contractor accepts the Government's written cancellation and does not claim costs were incurred.
The purchase order is considered cancelled once the contractor submits a claim for costs incurred as a result of the Government's written cancellation.
The purchase order must be terminated in accordance with FAR part or FAR
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock